Australian electrical — design, install, certify

Draw the job once.
Build it. Prove it.

SiteTwin is a digital twin of your electrical installation. Every board, circuit, cable and outlet exists as a real object — designed in the office, verified on site by the sparky doing the work, and exported as a signed certificate the day you finish. Built in Australia, to AS/NZS 3000, for Australian electrical contractors.

DESIGNED BY A LICENSED ELECTRICIAN
Aidan Green — licensed electrician & licensed builder, NSW
DATA ENTRY, NOT FIVE
0
REDRAWN AS-BUILTS
SAME DAY
CERTIFICATE ISSUED

The same job,
typed in five times

Consultant's drawing set
Estimator's spreadsheet
Cable schedule
Marked-up as-builts
Certificate, retyped from memory

01 — Layers & objects

Not lines on a drawing. Objects that know what they are.

A CAD line is dumb — it can't tell you its cable size, who installed it, or whether it passed an insulation resistance test. In SiteTwin every element is a typed object carrying its own specification, its own status and its own history.

Because they're objects, they stack into layers you can turn on and off — structure, containment, power, lighting, data, fire — and every layer stays in register with the others. Change a board and the circuits under it know.

One object, one truth — spec, install, test and sign-off all hang off the same record.
Change the spec and every downstream document updates — schedule, plan, certificate.
Nothing is "as-built later". As-built is just the object's current state.
LAYER STACK — LEVEL 3
Architectural baseLOCKED
Containment — tray, conduit, ladder142 OBJ
Power — boards, subs, circuits, GPOs318 OBJ
Lighting & controls204 OBJ
Data & comms96 OBJ
Fire & emergencyHIDDEN
OBJECT — SELECTED AWAITING QA
GPO — Double, 10A O-3184
CIRCUIT
C-07/L3/GPW
BOARD
DB-L3-W
CABLE
2.5mm² TPS Cu
PROTECTION
20A C-curve RCBO
HEIGHT AFFL
300 mm
CLAUSE
3000 — 4.4.2
2026-07-08 — SPECIFIED — R. HALE
2026-07-19 — ROUGHED IN — J. NGUYEN
2026-07-24 — FITTED OFF — J. NGUYEN — PHOTO ×2
DISTRIBUTION HIERARCHY — HARBOUR ST
Main switchboard
MSB — 800A TP&N
3 SUBS
DB-L3-E — East
160A · 24 ways · 18 used
DEFECT ×2
C-11 — Lighting eastIR FAIL
C-12 — GPO eastPASS
DB-L3-W — West
160A · 24 ways · 21 used
COMPLIANT
DB-MECH — Plant
250A · 18 ways · 11 used
AWAITING QA
SPARE WAYS
16
MAX DEMAND
612A
HEADROOM
23%

02 — Boards & hierarchy

The whole installation, from main switch to final outlet

Boards aren't a spreadsheet tab — they're a tree. The MSB knows its subs, each sub knows its ways, each way knows its circuit, and each circuit knows every object hanging off it.

So the questions that normally take a phone call answer themselves: how many spare ways are left on L3 East, what's actually loaded on this sub, which circuits are still unverified, and what happens to max demand if the tenant adds three more workstations.

Load & demand, live
Diversity and max demand recalculate as circuits are added or changed.
Roll-up status
A failed circuit turns its board red and its level amber. Nothing hides.
Real schedules
Board schedules print from the model — they can't drift from what's installed.
Variation trail
Every change is attributed and dated — useful when the claim is disputed.

03 — Cable schedule

The schedule isn't a document. It's a view of the model.

Cable sizing, volt drop and protection coordination are calculated from the objects themselves — route length from the containment layer, load from the circuit, method from the installation condition. Change a run and the schedule changes with it.

Volt drop checked live
Flagged against 3% / 5% before anyone pulls cable.
Ordering, not guessing
Drum lengths and totals come off real routes with real allowances.
CABLE SCHEDULE — LEVEL 3 — 86 RUNS
CircuitFrom → ToCableLengthMethodV-DropProtectionStatus
C-04/L3/SB2AMSB → SB2A4C 95mm² Cu48 mTray1.2%160A MCCBVERIFIED
C-07/L3/GPWDB-L3-W → W12.5mm² TPS34 mConduit2.1%20A RCBOAWAITING QA
C-11/L3/LTEDB-L3-E → LTE1.5mm² TPS72 mCeiling void5.4%16A RCBODEFECT ×2
C-14/L3/MECHDB-MECH → AHU24C 16mm² Cu26 mLadder0.9%63A MCBNOT STARTED
FLAGGED

C-11/L3/LTE exceeds 3% volt drop at 72 m on 1.5mm². Model suggests 2.5mm², or splitting the run at the east riser. Raised automatically at design stage — not discovered at commissioning.

04 — Plan views

Every drawing is generated, never maintained

Filter the model by layer, by board, by circuit, by installer, by status — and you have a drawing. A rough-in sheet for Tuesday's crew, a defects plan for the QA walk, a services coordination view for the builder, a set of as-builts for handover.

They can't go stale, because there is nothing to update. The drawing is a question you asked the model this morning.

STATUS BY CIRCUIT BY BOARD BY INSTALLER DEFECTS ONLY
LEVEL 3 — POWER — STATUS VIEW1:100
OFFICE EAST PLANT OPEN FLOOR WEST C-11 · V-DROP 5.4%
VERIFIED AWAITING QA DEFECT BOARD

05 — On site — electrician view

Built for one glove off, halfway up a ladder

The site view is not the office view shrunk down. It's a task list for today's circuits, big enough to hit with a gloved thumb, legible in full sun, and it works in a basement with no signal — everything queues and syncs when you walk back out.

Scan the board label, see what's on it, tick off what you fitted, photograph the termination, punch in your test results. That's the whole interaction. No paperwork tonight, because the paperwork happened while you worked.

"I designed this screen at a switchboard, not at a desk. Every field on it is one I got sick of writing on the back of my hand." AIDAN THOMAS GREEN — FOUNDER
Offline first
Basements, risers, lift shafts. Queue locally, sync later.
48px targets
Gloves on, screen wet, sun overhead. Still hits.
Photo = evidence
Attached to the object, stamped with who, when and where.
Test results in situ
IR, loop, RCD trip — typed once, at the board, into the record.

06 — Compliance & certification

The certificate writes itself, because you already did the work

Every state calls it something different and wants it in a different format — a CCEW in New South Wales, a COES in Victoria, a Certificate of Compliance in Queensland, an eNotice in Western Australia. All of them are an evening job: dig through photos, ring the apprentice, reconstruct test results from a damp notebook, hope the numbers match the installation.

In SiteTwin, every circuit already carries its test results, its installer, its date, its photos and its clause references — captured at the board when the work happened. The certificate is a render of data you've been collecting all job. Pick your state, press export, sign, send it to the customer and the network operator.

NSW — CCEW VIC — COES QLD — COC WA — eNOTICE SA · TAS · NT · ACT
Blocked if incomplete: unverified circuits and open defects stop the export, with a list of exactly what's missing.
Full evidence pack attached — as-built plans, test schedule, photos, variation trail.
Retained against the licence holder for the statutory period, so a query in three years takes a minute, not a weekend.
PRE-EXPORT CHECK
86 circuits tested & recordedPASS
4 boards verified against modelPASS
318 objects photographedPASS
2 open defects — C-11/L3/LTEBLOCKING
Certificate of compliance
Electrical work — NSW
JOB — HARBOUR ST, SYDNEY NSW — LEVEL 3 FITOUT
LICENCE — NSW 214 883C — J. NGUYEN
STANDARD — AS/NZS 3000:2018
CIRCUITS — 86 TESTED · 86 PASS · 0 OUTSTANDING
ISSUED — 2026-07-26 · CUSTOMER + NETWORK OPERATOR
AS-BUILT PLANS ×6 TEST SCHEDULE PHOTOS ×318 VARIATION TRAIL
One model, end to end
01
Design
Lay out boards, circuits and objects against the architectural base.
02
Specify
Cable, protection and volt drop resolved before anyone orders drum one.
03
Install
The crew works the task list and ticks objects off at the board.
04
Verify
QA walks a defects plan. Test results land on the object, not a notebook.
05
Certify
Your state's certificate and the full evidence pack export the day the job finishes.
What's next

Electrical first. The rest of the services follow.

The object model is trade-agnostic — a hydraulic riser and a mechanical plant run behave like a circuit. Electrical is where the compliance burden is heaviest, so that's where we started.

Electrical
AVAILABLE NOW
Hydraulic
IN DESIGN
Mechanical
PLANNED
Structural
PLANNED
Aidan Green, founder of SiteTwin — licensed electrician and licensed builder
NSW CONTRACTOR LICENCE
401889C
Electrical wiring work
General building work

Both classes on one licence. Check it yourself on the NSW Fair Trading register.

Why this exists

I hold both licences. I've been on both ends of this argument.

I'm a licensed electrician and a licensed builder. That's an unusual pair of tickets, and it means I've been the sparky handing over a certificate, and the builder chasing one.

Both sides waste the same weeks on the same problem: the installation exists in someone's head, in a marked-up PDF, in a text message, and in a notebook in a ute — and never in one place. So the as-builts get redrawn from memory, the CCEW gets reconstructed on a Sunday night, and when something's questioned two years later nobody can prove what was actually installed.

SiteTwin is the tool I wanted on my own jobs. Not a project management app with an electrical module bolted on — a model of the actual installation, built by someone who has terminated the circuits and signed the certificate.

If a screen in this product annoys you, tell me. I still hold the licence, and I still care what it says.
Aidan Thomas Green FOUNDER, SITETWIN
LICENSED ELECTRICIAN & LICENSED BUILDER

Built here

Australian software for Australian sparkies

SiteTwin was written in Sydney by people who have stood in a riser at 6am with a torch in their teeth. It speaks AS/NZS 3000, not a translated American standard. It knows what a CCEW is, what an RCBO is, and why the volt drop rule matters on a 72 metre lighting run.

Support is in your time zone. Nobody's going to ask you what a "receptacle" is.

STANDARDS
AS/NZS 3000, 3008 and 3017 built into the model — clause references on every object.
EVERY STATE
Certificate formats and licence rules for all eight states and territories.
YOUR RECORDS, YOURS
Export the full job — model, evidence pack, certificates — any time, in open formats.
AEST SUPPORT
Real people, on the tools before they were on the phones.

Bring your next job in with the paperwork already done

Twenty minutes, your own drawing set, your own boards. We'll build a live twin of one level while you watch — anywhere in Australia.

Contact

Tell me about the job

Send a level, a board schedule, or just the address. I'll come back within one business day with a live twin of part of it — no obligation, no sales deck.

OFFICE
Level 4, 29 Kiora Road
Miranda NSW 2228
EXISTING CUSTOMER
Sign in to app.sitetwin.io →

We reply within one business day, AEST.